Eco Tourism
Above is a photo of work in progress at BRL. This ‘mock-up’ chalet is now complete and all remaining 8 rooms should be ready by the end of June. We deliberately programmed construction to complete one twin chalet ahead of the others. This approach has proved very useful and has allowed us time to tweak the design without big cost penalties.The photo shows the concrete base of a spa bath which has been installed in six of the ten chalets. As well as being the area of design which as been most ‘tweaked’, this bath also...