BRL Renovation: Demolitions
By Ian Hall
Since 2006 we have been working on the renovation of Borneo Rainforest Lodge. 24 of the 31 rooms are complete and we have finally started the Big One – renovation of the Main Lodge building itself.
This is a big deal because it means shutting down the hotel for over two months and doing a major shopfitting type job under difficult conditions.
Shop fitting type; because work will progress around the clock to minimise the closure time.
Difficult conditions; in normal weather it takes a 4WD lorry 4 hours to reach the lodge. Right now it is the rainy season meaning the road is a quagmire and two bridges are down making the journey impassable to all but small pick-up trucks.
So far the contractor has succeeded in pulling the lodge apart and now has two months in which to put it back together!